Construction crews are installing bathroom tile, as well as electric and lighting fixtures at Academy Lofts. Walls are being primed and painted, and after the holiday, the flooring contractor will begin work. This will allow for millwork installation, appliances and other finishing work to follow. Units are expected to go on the market in February 2021.