Foundation work for the new buildings being constructed as part of the Willkommen project is still ongoing at 1521 Vine Street and 1602 Pleasant Street. Meanwhile, construction will begin on the Republic Street site once the first-floor podium is complete. Underground utility coordination is taking place for the new building that will occupy 213 Woodward Street. All 16 historic buildings are currently undergoing renovations, with structural and masonry repairs and interior framing as the focus. Tile and hardwood flooring are being installed/updated across each site.