Work on Perseverance is steadily moving along. At 1505 Vine Street, fourth-floor framing is underway and fifth-floor trusses and sheathing are going up, and roof trusses were lifted last week. Flooring and walls are the focus at 1511 and 1517 Vine Street, with tile and hardwood floor going down at the former, and floor repairs being completed at the latter. Drywall, plaster and interior painting will round out work this month at both of those sites. Exterior lighting and storefront installation are taking place at 1513-1515 Vine, along with courtyard painting.