project-update 12893

Posted on August 26, 2020 by sujvary

Each building included in the Perseverance project is progressing. Columns and masonry walls at 1505 Vine Street are in progress, while the new storefront is being installed at 1511 Vine Street. Insulation is going in at 1513-1515 Vine and electrical work is being completed at 1517 Vine, with drywall rounding out work at both of the latter sites.