Each building that makes up Perseverance progressed toward completion during the month of June, with exterior painting ongoing at each site. Foundation walls continue to go up at 1505 Vine Street, and roofing repairs are being completed at 1513-1515 Vine Street, in addition to ongoing mechanical, electrical, and plumbing work. The building at 1517 Vine is currently undergoing framing and masonry repairs.