Posted on September 3, 2019 by kdriscoll
Significant progress was made on the upper levels of the 4th & Race project site during August. Crews poured the deck for the third floor and the east ramp and formed the decks for the fourth floor. They also finished pouring all concrete and columns on the third floor and completed forming, reinforcing and laying the electrical conduit for the fourth pour on the fourth floor. For additional details, subscribe to regular project updates, and refer to the archive for past updates.