Posted on July 31, 2019 by kdriscoll

Crews are working to finish all electrical, plumbing, and mechanical rough-ins, and drywall hanging is underway throughout the Behlen building. Elevator installation will begin in the next couple weeks. Exterior masonry repair is complete, and exterior painting will begin in August.