project-update 11566
Posted on July 31, 2019 by kdriscoll
At Court & Walnut, crews are continuing to install exterior panels on the building. They are also framing, and completing wall finishes on the Kroger floors. In the past few weeks, crews have also installed glass, cabinets and interior doors on multiple floors. The new 35-space Central & Walnut Parking Lot is officially open, and it is conveniently located across the street from the Court & Walnut project. In the coming weeks, crews will work on enclosing the building. For additional details, subscribe to regular project updates, and refer to the archive for past updates.