Posted on July 1, 2019 by kdriscoll
Construction is progressing at the 4th & Race project site, with the boring operation and all underground work completed in June. Masons have installed foam for the slab on the foam ramps, and crews continued forming decks and columns for pours at multiple areas of the building. For additional details, subscribe to regular project updates, and refer to the archive for past updates.