project-update 11470

Posted on July 1, 2019 by kdriscoll

Crews finished installing the rooftop AC units at the Elm Industries, and they are currently working on forming the elevator shaft and framing the elevator lobbies. Interior framing is occurring on the third and fourth floors, and drywall is hanging on the second floor. In the coming weeks, the exterior of the building will be painted.