At the Court Street Condos, crews are hard at work painting the exterior of the building. They will move west to east in the coming weeks as they continue paint work. In the west group of buildings, interior painting has started. Crews are also laying bathroom tile and finishing drywall installation in the west group of buildings. Meanwhile, in the east group, drywall installation will begin soon.