project-update 11229
Posted on April 30, 2019 by kdriscoll
At the Court Street Condos, crews are hard at work in both the east and west sets of buildings. In the east group of buildings, crews are currently working on framing and installing fire-rated ceilings, in addition to continuing work on mechanical, electrical and plumbing rough-ins. Drywall installation continues in the west groups of buildings, as do stair repairs. Meanwhile, insulation work and fire escape modifications are ongoing at all buildings. Additionally, framing for the storefronts has been completed.