project-update 11219

Posted on April 30, 2019 by kdriscoll

Great progress has been made at Elm Industries this month. Crews are pouring new first-floor concrete and have been working to enclose the new elevator lobby. On the second floor, drywall installation has begun, and on the third and fourth floors, framing and rough-ins are ongoing. At the western elevation, window installation is in progress and work will begin shortly on the east façade (including the cornice rebuild).