Posted on February 25, 2019 by kdwenger
The Columbia renovation is progressing nicely as crews have nearly completed the interior framing for the south half of the building and continue working north. Mechanical, electrical, plumbing, and data rough-ins are currently underway, and crews will begin insulating ceilings and installing drywall shortly.