Posted on February 25, 2019 by kdwenger
Frigid temperatures and heavy rained slowed construction on the 4th and Race project this month, but crews worked diligently to continue progress on the project’s foundation and were able to effectively install a Storm Sewer connection on Elm Street. Additionally, existing foundations were removed along 4th and Race streets, crews finished grouting micro piles, and prep work for installing auger cast piles was completed. For additional details, subscribe to regular project updates, and refer to the archive for past updates.