At Beecher Flats, the installation of cabinets and countertops is now complete. Installation of electrical, HVAC and plumbing fixtures has been completed, as well. Storefront installations are moving forward, in addition to appliance installs.
At Rennen, cabinets have been installed and the interior paint has been completed. Work on the exterior is underway, with the installation of storefronts and siding ongoing. The interior is still in progress, including installation of appliances, countertops, electrical, HVAC, and plumbing fixtures.