Work throughout the building continues at the Court & Walnut project site. Tile and exterior metal framing have been installed along the building’s south elevation, while exterior tile work continues along the north and west elevations. The cooler, walk-in refrigerator and spray insulation have been installed in the Kroger space, as overhead MEP work continues. Crews have also begun installing the sprinkler pipes and in-wall MEP in the space. CMU block infill is underway for the elevator, as controls are being installed in the elevator control rooms. Over the next few weeks, elevators will be delivered and installation will begin. Lastly, the building is expected to obtain permanent power in the coming days. For additional details, subscribe to regular project updates, and refer to the archive for past updates.