Posted on September 28, 2018 by aatkinson
To date, crews have made progress from the basement to the ninth floor on the Court & Walnut mixed-use development. The topping slab on the garage ramp was recently completed, as well as the CMU walls at the loading dock adjacent to the Hamilton County Building. Miscellaneous CMU infills continue on the loading dock roof, as overhead MEP work continues at the loading dock and on the second floor. Crews recently placed concrete for decks on the eighth floor and are forming the ninth-floor deck. Concrete has also been placed for the shear walls and columns. Prep and connection work for the lobby stairs is underway, as well as various steel framework installation for the elevators. The installation of insulated freezer panels for the highly anticipated Kroger grocery store has begun, and various waterproofing work continues. In the coming weeks, crews will begin installing the curtain wall and lobby stairs. For additional details, subscribe to regular project updates, and refer to the archive for past updates.