project-update 10374
Posted on August 31, 2018 by aatkinson
At Beecher Flats, the brick portion of the façade is nearing completion. When finished, crews will begin working on the façade at Rennen. Additionally, shower tile and hardwood floors are being installed at Beecher Flats. Drywall work is nearing completion at Rennen, as crews prepare for Gypcrete to be poured in the coming weeks. Lastly, both buildings now have permanent power.