project-update 10372

Posted on August 31, 2018 by aatkinson

Crews continue to make progress at Court & Walnut with each passing day, and work is now taking place from the basement to the seventh floor. The retail awning was recently completed, as well as the sixth-floor concrete pours. Overhead MEP rough-ins continue, and in-wall rough-ins are just beginning. Interior framing work is wrapping up on the first and second floors, and stairs are being installed. Prep work for the topping slab on the speed ramp and second floor is also underway. At the loading dock, masonry work is ongoing as roofing is being installed. Lastly, crews have begun forming and pouring the seventh-floor deck. In the coming weeks, exterior tile work will begin. For additional details, subscribe to regular project updates, and refer to the archive for past updates.