project-update 10305
Posted on July 31, 2018 by aatkinson
At Beecher Flats, drywall work is finished, and crews have poured gypcrete. Exterior brick is being set and should be complete in the coming weeks. The parking lot base course has been poured and exterior fiber cement siding is now being placed. Crews will also begin priming the interior walls in the near future. At Rennen, utility inspections are officially complete and rooftop units are being set. Exterior brick is being set and should be completed in the coming weeks, as insulation continues to be installed.