project-update 10220

Posted on June 28, 2018 by aatkinson

Crews have begun hanging drywall on the second and third floors of Beecher Flats. The rooftop units are being set as exterior brick setting continues. Insulation is being installed throughout the building, and the team will begin paving the parking lot in the coming days. Rennen recently passed its framing inspection, and utility rough-ins have commenced for all trades. To-date, the windows are 98% installed. In the coming weeks, crews will begin drywall and exterior brick work.