project-update 10151

Posted on May 30, 2018 by aatkinson

Work is progressing nicely at Rennen & Beecher Flats, as crews complete various tasks throughout the project site. Currently, Rennen is being framed and utility rough-ins will begin in just a few weeks. Beecher Flats has now been completely framed, as window installation and utility rough-ins near completion as well. Masonry work has also begun at Beecher Flats and will continue for the next several weeks. Crews are currently pouring the sidewalks on Race, 15th and Pleasant streets, and in the coming weeks, drywall installation will start at Beecher Flats. The parking lot at the back of the project site will also be poured in the near future.