project-update 10150

Posted on May 30, 2018 by aatkinson

Crews have now made progress from the basement to the third floor at the Court & Walnut project site. As MEP rough-ins continue in the basement, the forming and pouring of columns and walls continues on the first floor. The second-floor columns and concrete deck are now complete and shoring and forming for the helical ramp continues. On the third floor, the installation of rebar for the deck is underway, and crews recently completed the first and second concrete pours. In the coming weeks, crews will complete the third-floor columns and walls. For additional details, subscribe to regular project updates, and refer to the archive for past updates.