Posted on April 30, 2018 by aatkinson

At the Court & Walnut project site, pile caps and grade beams are now complete. MEP rough-ins continue in the basement, as the forming and pouring of first-floor columns and walls also continues. On the second floor, the first and second concrete pours are now complete, and shoring and forming for the elevated deck continues. Forming and pouring for the columns and walls on the second floor is also underway. For additional details, subscribe to regular project updates, and refer to the archive for past updates.