Posted on July 9, 2013 by amileham

In Phase I of the project, seven of the 11 Mercer Historic units are currently under contract. Structural framing for the One Mercer mixed-use building on Vine Street and the Mercer Townhomes on Mercer Street is nearly finished. The buildings will be completed in Fall 2013. In Phase II of the project, 10 or 11 rehabs are under construction. Some are in demolition phases while others are ready for framing inspections to hang drywall. The new construction building will start piles in mid July.