project-update 9055

Posted on October 30, 2017 by aatkinson

Work is progressing nicely at Abington, Race & Pleasant. Construction is wrapping up on Race Street units 1523 – 1527, as well as on units 1529-1531, with final paint and finishing touches taking place now. Site work is ongoing, with concrete walkways, residential gates, and fencing being installed. In units 1533-1535, drywall and hardwood flooring are also being installed. Painters will move from the first few properties down to this property as drywall work wraps up. Lastly, crews continue to work on the elevator at 33 Green Street, as kitchen cabinetry and hardwood flooring is being installed.