project-update 9732

Posted on March 29, 2018 by aatkinson

Steel has been set for both Rennen and Beecher Flats, and underground utilities are being roughed-in. Several pours of slab-on-grade have been made in Beecher Flats, primarily at the stairs, entrance ways, and in first-floor residential units. Interior framing work is complete at 1505 Race – the historic structure that is being integrated into Rennen – while framing work continues at Beecher Flats. Utility work will continue for the next few weeks, as well.