The south stair tower is now complete, and the metal stairs have been installed. Steel erection, which provides the structural shell of the building, is currently in the second of four phases. Structural masonry repairs are underway in the historic buildings, ensuring that the connections between the rehabilitated buildings and the new structure can be completed without complication. In the upcoming months, crews will install metal decking with subsequent concrete pours. Leasing information for the office and retail space is available on the 3CDC website.