project-update 9614

Posted on February 26, 2018 by aatkinson

Crews are making great progress in the basement area, with pile caps, columns, walls, and blindside waterproofing now complete. Stone grading and backfilling around the basement is currently underway, as well as the installation of the sump pump. Shoring and forming of the first floor has begun, as pile caps and grade beams continue being poured. Between the first and second floor, shoring and forming for the deck has also begun, and the concrete pour took place last week. For additional details, subscribe to regular project updates, and refer to the archive for past updates.