Posted on August 31, 2017 by aatkinson
Things are moving along nicely on the Abington Race & Pleasant project. The Race Street properties have begun to see site work, including the demolition of an old retaining wall at the rear of the property. A new retaining wall has been constructed in its place. Wood flooring is being installed in a number of the retail and office spaces, as storefronts are being installed at all commercial spaces, with glass currently going in. Site work at 33 Green Street is ongoing, and includes a new exterior back patio and ADA accessibility ramp. The existing storefront has been demolished, and a new wooden storefront has been built and installed in its place.