Posted on August 31, 2017 by aatkinson
The future home of Empower MediaMarketing is currently receiving both interior and exterior finishes. Final paint is being applied on the first floor, and carpet is being laid. Final paint is also being applied on the second floor, and carpet has been completely installed. Crews are hanging the interior doors, and Empower’s employee furniture has arrived on-site. Outside the building, sidewalks are being poured and cladding is being installed. Construction is on schedule for completion this fall.