March 2024 Updates

DUKE ENERGY CONVENTION CENTER

3CDC and the teams leading the design and construction management of the Duke Energy Convention Center (DECC) renovation project are currently producing construction drawings based on the evolving project design. In the coming weeks, Messer Construction will provide a Guaranteed Maximum Price (GMP) based on the completed design development drawings. GMP negotiations will follow with a goal of having an executed GMP in May. 3CDC, the City of Cincinnati, and convention center management are also in the process of determining the end use for the existing furniture and equipment currently at DECC. The second of 3CDC’s regular Convention District construction updates is scheduled to be sent out later today. Stay in the know with everything happening in the Convention District by subscribing to receive monthly construction updates.

THE ANNIE

At The Annie, the City of Cincinnati issued the final Certificate of Occupancy for the 16 mixed-income apartment units at 216-218 W 12th Street. All studio, 1-BR and 2-BR units feature new hardwood flooring, quartz countertops, brand new kitchen appliances, and in-unit laundry. These units will be available for immediate move-in later this month. Urban Sites, an Over-The-Rhine based property management company, will begin showings for interested tenants this week. Visit the Urban Sites website for more information.

At 210-214 W 12th Street, the installation of electrical and plumbing fixtures and interior painting in the remaining 12 units was recently completed. The project’s general contractor, Triversity Construction, will finalize punch list work in the coming weeks. Completion of the remaining 12 units is on track for this Spring.