project-update 19764
Posted on August 13, 2024 by ccurran
Façade demolition is now largely complete at Paycor headquarters, and crews are making steady progress on work throughout the building’s interior. The construction team is infilling the old escalator’s opening between Levels 1 and 2 with steel. Installation of both a new sprinkler system and HVAC ductwork is ongoing, and crews are currently completing framing work for tenant demising walls. Stay in the know with everything happening at Paycor Headquarters by subscribing to receive monthly construction updates.