At the Findlay Hub, construction is entering its final phases, with exterior work nearing completion and significant progress being made throughout the interior. The building’s curtain wall, windows, canopies, and exterior metal panels are now largely complete. Inside, many spaces, including childcare rooms, fitness areas, and locker rooms, have moved into the finishing stage, with painting, flooring, ceilings, and wall tile installation underway.
Key amenities are taking shape, as gymnasium flooring and court striping have been completed, while fitness areas continue to receive flooring and acoustical treatments. The elevator is fully installed, and crews are focused on final building systems work, including mechanical and electrical connections, lighting installation, and testing of plumbing and HVAC systems. Overall, the project is making steady progress toward completion.
Community members can now visit FindlayHub.org to submit their information and sign up for updates on membership and early childhood care enrollment as plans are rolled out.
Construction is officially underway on Findlay Flats, a project that will restore 10 historic buildings along the 1700 and 1800 blocks of Vine Street in Over-the-Rhine. Once complete, the development will deliver 45 residential units, including 22 affordable units for households earning at or below 80% of the Area Median Income (AMI).
On the 1700 block, crews have begun structural repairs and interior wall framing while continuing historic masonry restoration. On the 1800 block, historic window restoration, structural repairs, and floor patching are underway, with interior wall framing scheduled to begin in the coming days. Overall, the project is advancing steadily as these historic buildings are transformed into new mixed-income housing opportunities.