At the Findlay Community Hub, crews have completed structural steel installation and finished the slab-on-metal deck on the second floor, as well as the first-floor concrete slab-on-grade. Work on the exterior façade is progressing, with sheathing now underway. Interior framing has expanded throughout the building, including layout and framing in the cardio, gymnasium, and roller rink areas. Interior painting is in progress in the locker rooms and nearing completion at the pool. Fireproofing continues throughout the facility, while MEP rough-in and systems installation are advancing in multiple areas, including ongoing work in the roller rink and the start of hanger installation in administrative spaces.