This month, crews reached several construction milestones at the Findlay Community Center. Masonry wall construction for the pool and locker room areas was completed, and crews continued work on the gym. The slab-on-grade—a concrete foundation poured directly onto the ground—for the gym and locker rooms was finished, and crews will pour the roller rink area next. Underground utility work, including plumbing and electrical systems, also wrapped up across the site. Crews will focus on structural steel work beginning in January. Stay in the know with the transformative redevelopment projects in North OTR by subscribing to receive monthly construction updates.
At Crossroad Health Center, construction progressed both on-site and inside the 1715 Republic Street building. Concrete placement for the Race Street driveway was completed, along with all slab removals across the site, and sidewalk installation commenced. Inside 1715 Republic, first-floor metal stud framing was finished, and the exterior entrance canopy was installed. Drywall installation continued throughout the building. On the second floor, crews continued painting and began installing an acoustic ceiling tile (ACT) grid. All MEP rough-ins were completed, and crews installed windows on both floors. At the historic clock tower, crews completed interior stair repairs. Stay in the know with the transformative redevelopment projects in North OTR by subscribing to receive monthly construction updates.